Brick work in Cement Mortar 1:6 in foundation and plinth using common burnt clay bricks of class designation 75, including curing etc. complete.

F1 - BRICK WORK IN CM 1:6 UP TO PLINTH

Project / Reference No. / Item Designation
DESCRIPTION

QUANTITY

UNIT

RATE

AMOUNT

Labour: ( Details Per M3 )
Mason No.
Mazdoor (M) No.
Coolie (F)  No.
Waterman No.
Material + Carriage:
Bricks + Wastage No.
Carriage of Bricks No.
Cement Mortar 1:6 M3
Sub Total:

 

Sundries & Contingencies *** %  
Water + Electricity %  
Taxes (Contract / Sales etc.)  %  
Over Head + Profit  %  
Cost Per 1.0 M3 of Masonry work

 

         

            

Enter Current Rates for Labour, Material, Taxes etc. & Click Rate Button above.

*** Includes Hire cost of Pump for Water @ 0.50 %.
Use Cement Mortar Program Option to arrive at the Rate without Adding Sundries, Water, Contingencies, Electricity, Over Head and Profit.
Note: 
1. By changing the Cement Mortar Mix & its Rate in the above Table, we can get the Masonry cost for different Mortar Mix. Note that quantity of Mortar will remain unchanged in each case.
2. In general the constants above include labour involved in scaffolding.

S U M M A R Y

Labour Rs/M3         Material Rs/M3  OTHER Rs/M3 
Labour %                Material %         OTHER %        
Labour ÷ Material   %.  OTHER = Total Rate - Labour - Material- Carriage
Data as per IS: 7272 - Part - 1 - 1972.
This is a sample program from SUPER RATE ANALYSIS SOFTWARE.
For more info Contact:
Mr. Yusuf A. Agboatwala,
1802, Jamuna Amrut, 219, Patel Estate,
S. V. Road, Jogeshwari (West), 
Mumbai 400102.
Phone: 26783525
Cell: 9820792254
Email: yaa@supercivilcd.com
URL: www.supercivilcd.com